Canyon Resources announced on Thursday, November 26, a proposed equity raising of up to about A$70 million to finance the remaining development work at its Minim Martap bauxite mine in Cameroon’s Adamawa region. In a statement to the Australian stock exchange, the company also withdrew the findings of its definitive feasibility study after reassessing the development timetable and funding needs.
Eligible shareholders will be able to subscribe for one new share for every share held on December 1, at A$0.034 apiece. The non-underwritten offer, with tradable entitlements, is designed to finance the remaining development work and initial working capital ahead of the first shipments.
A funding threshold of A$48 million
Canyon estimates that raising at least A$48 million, combined with existing cash, would allow it to finish preparations for first exports, now targeted for June 2027. The proceeds will not cover the subsequent expansion of the project or debt service on the AFG Bank Cameroon facility, which will require further funding.
Funding delays in 2026 have prevented the company from carrying out planned railway investments. Canyon has therefore withdrawn its previous ore reserve estimates and financial projections while retaining the mineral resource estimates. Development is now expected to proceed with a more gradual increase in output.
Rail capacity shapes the export timetable
Canyon estimates that its existing rail fleet can transport around 35,000 tonnes per month. The company still needs to commission its infrastructure and finalise transhipment arrangements at the port of Douala. Seven locomotives have been delivered to the port, along with 140 of the 160 wagons ordered.
The company also plans to provide AFG with a revised development schedule and updated financial inputs if sufficient funds are raised. A visit to the site by the bank’s representatives is expected in December.