In Gabon, directly awarded public contracts accounted for 93.3% of procurement value recorded between January and August 2025, up from 89.7% over the whole of 2024. The figures, published in a World Bank public finance review in September 2026, raise a pressing question for a government facing tight fiscal space. How can the state demonstrate value for money on public works when most procurement value is awarded without competitive tendering?

The difference is 3.6 percentage points, although the second period covers only the first eight months of 2025 rather than a full year. The World Bank traces the particularly high share by value to a small number of large awards, notably at the Ministry of Public Works. Direct awards can be justified in particular circumstances, but their dominance narrows the opportunities to compare suppliers’ offers and prices across the government’s procurement portfolio.

Direct contracting dominates awarded value

In Share of public procurement value, %

Direct awardsOther methods0204060801002024Jan-Aug 2025Direct awards · 2024 : 89.7 Share of public procurement value, %Direct awards · Jan-Aug 2025 : 93.3 Share of public procurement value, %Other methods · 2024 : 10.3 Share of public procurement value, %Other methods · Jan-Aug 2025 : 6.7 Share of public procurement value, %Source: World Bank, Gabon Public Finance Review 2026, Chapter 4, p. 56. 2025 data Janu… · BiFinances

Source: World Bank, Gabon Public Finance Review 2026, Chapter 4, p. 56. 2025 data January-August.

Competitive procedures account for a small share of value

All other procurement methods combined represented a calculated 10.3% of awarded value in 2024 and 6.7% in January-August 2025. These percentages measure the value of contracts, not their number. A limited group of expensive infrastructure contracts can therefore dominate the totals without accounting for most individual procurement decisions.

The review identifies several factors behind the reliance on direct contracting, including weak project planning, pressure to execute budgets late in the year, limited technical capacity among some procuring entities and risk-averse officials operating under strong ex-post controls. Awards are concentrated particularly in public works and construction, where individual projects can involve considerable sums.

The issue reaches beyond the legal form of an award. Competitive tendering cannot by itself guarantee efficient spending, but it exposes competing bids, selection criteria and prices to scrutiny. Direct awards can shorten procurement in justified cases. When they become the norm by value, it becomes harder to assess competition and whether taxpayers are obtaining good value. The World Bank recommends stronger investment planning, publication of contracts and electronic procurement.

A larger state budget has not translated into more social spending

Procurement practices sit within a growing public spending envelope. Government expenditure averaged around 20% of GDP in 2016-2022 before rising to approximately 25% in 2023-2024. Yet the increase in total outlays was not matched by a comparable shift towards health, education and social protection.

In 2024, general public services took 47% of the budget in the functional spending classification, compared with 13% for education, 4% for health and 2% for social protection. Other government functions together accounted for the remaining 34%. This breakdown by function is different from an economic classification of spending into wages, purchases and investment.

How the 2024 budget was allocated

In Share of government spending, %, 2024

Select a bar to see its details.

Source: World Bank, Gabon Public Finance Review 2026, Chapter 3, p. 3. Other functions = 100 less the four reported functions.

Download

On that separate economic basis, the wage bill absorbed 27% of total expenditure in 2024, while special-purpose funds and other items represented about 26%, and capital investment 16%. Public wages equalled 7.1% of GDP. Social-sector allocations averaged around 4% of GDP over 2022-2024, less than half the Sub-Saharan African average reported by the World Bank.

The spending choices have consequences for public services. The report records 0.5 physicians per 1,000 people and finds that a substantial share of pre-primary teachers lack formal professional training. Spending on social safety nets was just 0.03% of GDP in 2024, leaving a particularly small financial envelope for targeted support.

Debt and limited tax receipts constrain the choices

The persistent weakness of non-oil taxation makes these trade-offs more acute. Non-oil tax revenue averaged 10.5% of GDP between 2014 and 2024. Tax exemptions and collection difficulties are among the factors identified by the World Bank. This leaves recurrent spending obligations exposed to the volatility of oil receipts and global commodity cycles.

Pressure is also evident in debt and cash management. Public debt payment arrears reached 3.5% of GDP in late 2025, while combined liabilities at several major state-owned enterprises exceeded 8% of GDP at the end of 2024. Those obligations restrict the financing available for infrastructure and services regardless of how future contracts are awarded.

The World Bank recommends more competitive purchasing, improved oversight of state-owned enterprises, tighter budget execution and more resources for essential services. It estimates that a package of reforms could yield net fiscal gains of between 1.8% and 5.3% of GDP, depending on the scenario. Its review also finds that actual government spending averaged 125% of original budget allocations over 2022-2024.